2008 AMC 12A Problem 1

Below is the professionally curated solution for Problem 1 of the 2008 AMC 12A, from LIVE by Po-Shen Loh. You can also try the full timed exam, view all 2008 AMC 12A solutions, or check the answer key.

All of the real AMC 8, AMC 10, AMC 12, and AIME problems in our complete solution collection are used with official legal permission of the Mathematical Association of America (MAA).

Concepts:ratio and proportiondate and time

Difficulty rating: 800

1.

A bakery owner turns on his doughnut machine at 8 ⁣: ⁣308\!:\!30 am. At 11 ⁣: ⁣1011\!:\!10 am the machine has completed one third of the day's job. At what time will the doughnut machine complete the job?

1 ⁣: ⁣501\!:\!50 pm

3 ⁣: ⁣003\!:\!00 pm

3 ⁣: ⁣303\!:\!30 pm

4 ⁣: ⁣304\!:\!30 pm

5 ⁣: ⁣505\!:\!50 pm

Solution:

From 8 ⁣: ⁣308\!:\!30 am to 11 ⁣: ⁣1011\!:\!10 am is 22 hours 4040 minutes, or 160160 minutes, to complete one third of the job.

The whole job then takes 3160=4803 \cdot 160 = 480 minutes, or 88 hours. Adding 88 hours to 8 ⁣: ⁣308\!:\!30 am gives 4 ⁣: ⁣304\!:\!30 pm.

Thus, D is the correct answer.