17.

A straight concrete sidewalk is to be 33 feet wide, 6060 feet long, and 33 inches thick. How many cubic yards of concrete must a contractor order for the sidewalk if concrete must be ordered in a whole number of cubic yards?
22
55
1212
2020
more than 2020
Answer: A
Concepts:volumeunit conversion
Small hint:
First convert 33 inches to feet: 3 in=14 ft3 \text{ in} = \dfrac14 \text{ ft}
Big hint:
Find the volume in cubic feet, then divide by 2727 since 11 cubic yard =27= 27 cubic feet
Solution:
The thickness is 33 inches =14= \dfrac14 foot, so the volume is 3⋅60⋅14=453 \cdot 60 \cdot \dfrac14 = 45 cubic feet.
Since 11 cubic yard =27= 27 cubic feet, this is 4527=123\dfrac{45}{27} = 1\dfrac23 cubic yards. Rounding up to a whole number, the contractor must order 22 cubic yards.
Thus, the correct answer is A .
LIVE by Po-Shen Loh
Programs

LIVE Classes

Self-Paced Classes

Stars

Scholarship

About Us

Who Is Po-Shen Loh?

Email Contact

Newsletter

Jobs

Become a Star

For a more Thought Full world.

© 2026 Expii, Inc.